Review Agenda Item
Meeting Date: 8/8/2022 - 7:00 PM
Category: Consolidated Motion
Type: Action
Subject: 13.15 Change Order #4B Between Mountain View Los Altos High School District and Galeb Paving, Inc. to Provide Services Related to the Los Altos High School New Classroom, Engineering Labs and Auxiliary Gym Project
LCAP (Local Control Accountability Plan) Goal:
Enclosure
File Attachment:
LAHS CR_Galeb CO #4B_08.08.22.pdf
Summary: Mountain View Los Altos High School District is requesting Change Order #4B with Galeb Paving, Inc. be ratified:
- Spoils off haul that was generated by others and left in the work area of Galeb. Also, demolition limits were increased per asphalt removal as noted.
- Reclamation of winterization materials and re-excavation of bio retention planter areas.
- Repair broken sanitary sewer line caused by Sausal on 7/9 in order to maintain scheduled concrete pour.
- Excavate silting basin per construction manager's direction onsite.
- Import of topsoil indirectly caused by request for information 453 response, and Department of Toxic Substances Control (DTSC) requirements. Topsoil added was placed in the planter area, and orange fence material was added under the subgrade.
- Remove and replace asphalt where the project trailer was located. Added asphalt was due to previous patching by others and existing areas. The cost noted is to remove all of the areas noted and replace with new asphalt.
Funding: $70,046.21
Bond (change order is within budget)
Recommendation: Ratify Change Order #4B between Mountain View Los Altos High School District and Galeb Paving, Inc. to provide services related to the Los Altos High School New Classroom, Engineering Labs and Auxiliary Gym project.
Approvals:
Recommended By:
Signed By:
Irene Aguilar - Administrative Assistant
Signed By:
Mike Mathiesen - Associate Superintendent
Signed By:
Nellie Meyer - Superintendent
Vote Results:

Original Motion
Member Debbie Torok Moved, Member Fiona Walter seconded to approve the Original motion 'Ratify Change Order #4B between Mountain View Los Altos High School District and Galeb Paving, Inc. to provide services related to the Los Altos High School New Classroom, Engineering Labs and Auxiliary Gym project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Phil Faillace     Yes
Sanjay Dave     Yes
Debbie Torok     Yes
Catherine Vonnegut     Yes
Fiona Walter     Yes