16.33 Change Order #10A Between Mountain View Los Altos High School District and Gonsalves & Stronck to Provide Services Related to the Los Altos High School Facility Repairs Inc. 1&2 – 500 Wing Replacement Project
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
Mountain View Los Altos High School District is requesting Change Order #10A with Gonsalves & Stronck be ratified: - Furnish and install an additional 6 Amp power supply at the Verkada control panel in new 500 building’s IDF room as described in ASI #003.2. This is to accommodate District’s request to change the security system from Lenel to Verkada. - Provide a wrapped drywall finish in lieu of wood trim at the interior side of all windows and storefronts as described in ASI #17. The cost below is the difference between the added cost for drywall and credit for wood trim. - Provide and install additional flashing and trim for exterior metal panel penetrations at (4) electrical boxes, a water spigot box, and (14) down spout brackets. The contract drawings show a detail for attaching downspouts to the wall, however, the detail did not describe how to treat the penetrations through the metal paneling.
|
Funding:
|
$26,853.00 Bond (change order is within budget)
|
Recommendation:
|
Ratify Change Order #10A between Mountain View Los Altos High School District and Gonsalves & Stronck to provide services related to the Los Altos High School Facility Repairs Inc. 1&2 – 500 Wing Replacement project.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Irene Aguilar - Administrative Assistant
|
|
Signed By:
|
|
Mike Mathiesen - Associate Superintendent
|
|
Signed By:
|
|
Nellie Meyer - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Phil Faillace Moved, Member Esmeralda Ortiz seconded to approve the Original motion 'Ratify Change Order #10A between Mountain View Los Altos High School District and Gonsalves & Stronck to provide services related to the Los Altos High School Facility Repairs Inc. 1&2 – 500 Wing Replacement project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 4 Nay: 0. | The motion Carried 4 - 0 | | | Phil Faillace | Yes | Sanjay Dave | Yes | Thida Cornes | Yes | Esmeralda Ortiz | Yes | |
|
|
|
|
|
|