Review Agenda Item
Meeting Date: 5/23/2022 - 7:00 PM
Category: Consolidated Motion
Type: Action
Subject: 17.21 Change Order #6C Between Mountain View Los Altos High School District and MK Pipelines, Inc. to Provide Services Related to the Los Altos High School New Classrooms, Engineering Labs, and Auxiliary Gymnasium Project
LCAP (Local Control Accountability Plan) Goal:
Enclosure
File Attachment:
LAHS CR_MK Pipelines CO #6C_04.25.2022.pdf
Futility Resolution 21-22-49 - LAHS CR & Gym - MK Pipelines.pdf
Summary: Mountain View Los Altos High School District is requesting Change Order #6C with MK Pipelines, Inc. be ratified:
- Furnish and install additional 240 lineal feet of 3" water
lines.
- Cost for Work Directive #30 was projected to be under
$10,0000; however, additional expenses were incurred
to lower utilities for lime treatment on T&M.
- Install new catch basin and pipe due to added curb near
planting area.
- Due to condition and location of an existing pipe, a
pressure test and backfill of trench was required for
proper tie-in of existing line.
- Install retaining wall with catch basin due to relocated
bio retention wall footings within classroom courtyard
and Tech building.
- Reconstruction of existing catch basin in planter area
and catch basin moved to new location.
- Raise and install rainwater leaders from downspouts to
collection boxes for all gutters and downspouts.
- Fix existing downspouts and install new ones, to divert
water from classroom building away from construction
zone. Existing sewer clean-out box dug out at higher
elevation to divert storm water from entering.
- Install 4 yards of slurry at end of bore pit to fill void
around 12' pipe.
- Repair sewer leak from an existing pipe, which was
leeching in native soil.
- Repaired broken 10” water main pipeline with C900 pipe
replacement and mechanical joint sleeves installed.
Funding: $66,458.77
Bond (change order is within budget)
Recommendation: Ratify Change Order #6C between Mountain View Los Altos High School District and MK Pipelines, Inc. to provide services related to the Los Altos High School New Classrooms, Engineering Labs, and Auxiliary Gymnasium project.
Approvals:
Recommended By:
Signed By:
Irene Aguilar - Administrative Assistant
Signed By:
Mike Mathiesen - Associate Superintendent
Signed By:
Nellie Meyer - Superintendent
Vote Results:

Original Motion
Member Fiona Walter Moved, Member Debbie Torok seconded to approve the Original motion 'Ratify Change Order #6C between Mountain View Los Altos High School District and MK Pipelines, Inc. to provide services related to the Los Altos High School New Classrooms, Engineering Labs, and Auxiliary Gymnasium project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Phil Faillace     Yes
Sanjay Dave     Yes
Debbie Torok     Yes
Catherine Vonnegut     Yes
Fiona Walter     Yes