Review Agenda Item
Meeting Date: 8/14/2023 - 7:00 PM
Category: Consolidated Motion
Type: Action
Subject: 14.25 Change Order #8D Between Mountain View Los Altos High School District and Atlas Pellizzari Electric to Provide Services Related to the Los Altos High School Student Services Building Project
LCAP (Local Control Accountability Plan) Goal:
Enclosure
File Attachment:
LAHS SS Bldg_Atlas Pellizzari Electric CO#8D_08-14-23.pdf
Summary: Mountain View Los Altos High School District is requesting Change Order #8D with Atlas Pellizzari Electric be ratified:
- Provide additional labor, equipment, and materials to sawcut & remove approx. 190 LF of the existing walkway at the 200 wing (to be replaced by others at a later date) to reroute new power and low voltage conduits due to unforeseen conflicts with the planter wall footings and existing underground utilities that already occupy the available space that was shown on the drawings. Also, provide concrete coring to tie-in to the 3 existing electrical vaults that were discovered to be encased in concrete preventing existing conduits from being removed or re-used.
Funding: $55,769.00
Bond (change order is within budget)
Recommendation: Ratify Change Order #8D between Mountain View Los Altos High School District and Atlas Pellizzari Electric to provide services related to the Los Altos High School Student Services Building project.
Approvals:
Recommended By:
Signed By:
Irene Aguilar - Administrative Assistant
Signed By:
Mike Mathiesen - Associate Superintendent
Signed By:
Nellie Meyer - Superintendent
Vote Results: