Review Agenda Item
Meeting Date: 11/18/2024 - 6:30 PM
Category: Consolidated Motion
Type: Action
Subject: 18.11 Change Order #7C Between Mountain View Los Altos High School District and MK Pipelines to Provide Services Related to the Los Altos High School Facility Repairs Inc. 1&2 – 500 Wing Replacement Project
LCAP (Local Control Accountability Plan) Goal:
Enclosure
File Attachment:
LAHS Facility & 500 Wing_MK Pipelines_CO#7C_11.18.24.pdf
MK Pipelines_Futility Resolution.pdf
Summary: Mountain View Los Altos High School District is requesting Change Order #7C with MK Pipelines be ratified:
- Facilities Repairs Inc 1: Provide the required utility locating, labor, material, and equipment to sawcut & demo concrete shown on the plans for the new water line installation outside of 300 West Wing. The contractor shall also chlorinate the new water line as part of the testing requirements.
- Facilities Repairs Inc 1: Provide trench plates for a 2-month rental duration to be installed between the 300 West and 800 Wings as needed to secure the trench as the installation of new water line
continues. The cost includes delivery and pickup. Utilizing Allowance worth of $2,760.00 from (C2) Trench Plates
- Facilities Repairs Inc 1: Provide overtime for a 5-man crew on Saturday, October 19th 2024, as needed to complete the water line cut & cap and backfill & compaction to maintain the construction schedule
- Facilities Repairs Inc 1: Provide the required labor, material, and equipment for investigative work to locate the existing live water line.
Funding: $30,096.21
Bond (change order is within budget)
Recommendation: Ratify Change Order #7C between Mountain View Los Altos High School District and MK Pipelines to provide services related to the Los Altos High School Facility Repairs Inc. 1&2 – 500 Wing Replacement project.
Approvals:
Recommended By:
Signed By:
Irene Aguilar - Administrative Assistant
Signed By:
Mike Mathiesen - Associate Superintendent
Signed By:
Eric Volta - Superintendent
Vote Results:

Original Motion
Member Thida Cornes Moved, Member Catherine Vonnegut seconded to approve the Original motion 'Ratify Change Order #7C between Mountain View Los Altos High School District and MK Pipelines to provide services related to the Los Altos High School Facility Repairs Inc. 1&2 – 500 Wing Replacement project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Phil Faillace     Yes
Sanjay Dave     Yes
Catherine Vonnegut     Yes
Thida Cornes     Yes
Esmeralda Ortiz     Yes