Review Agenda Item
Meeting Date: 8/14/2023 - 7:00 PM
Category: Consolidated Motion
Type: Action
Subject: 14.26 Change Order #3B Between Mountain View Los Altos High School District and McGuire & Hester to Provide Services Related to the Los Altos High School Student Services Building Project
LCAP (Local Control Accountability Plan) Goal:
Enclosure
File Attachment:
LAHS SS Bldg_McGuire & Hester CO #3B_08.14.2023.pdf
Summary: Mountain View Los Altos High School District is requesting Change Order #3B with McGuire & Hester be ratified:
- Remove and dispose of an existing electrical vault that conflicts with the footing for the walkway ramp wall at the north side of the Student Services Building. After the vault has been removed, Contractor shall provide backfill and compaction as needed to raise the grade to the required wall footing elevation.
- Demo approx. 150 LF of existing curb/asphalt that has been damaged by heavy equipment use throughout the course of construction and provide asphalt patch-back paving after the new concrete curb has been installed. New curb installation to be installed by the Site Concrete Contractor under a separate Work Directive/Change Order.
- Remove the temporary construction entrance, offhaul & dispose of rock and debris, recompact subgrade and install new asphalt paving.
- Provide labor and material on a premium time to add signage and wheel stops and perform striping of parking lot on Saturday 07/29/23. This work needs to be done on a Saturday in order to keep the parking lot traffic away so that the striping does not look faded or walked upon. This work will be done on an allowance B1 (Parking lot improvements: Wheel stops, painting, and striping) and is not an add to the contract value.
- Proposes to work on a Saturday on a premium time to install slurry seal for the parking lot. This work needs to be done on a Saturday in order to keep the traffic away from the parking lot for a smooth completion. The cost includes the scope of work and premium time. M&H will provide all labor and material in order to complete this work. The cost represents premium time only.
- Provide labor, equipment, and material to complete additional parking lot improvements that exceed the original $5k contract allowance (previously approved as WD #177).
- Provide labor and equipment as needed to remove a storm drain line in conflict with the foundation/footings on the south side of the student services building.
- Provide labor, equipment, and materials to complete grading adjustments for the sidewalk revisions at the 200 Wing due to issues with the design grades as described in CCD #57
Funding: $78,090.84
Bond (change order is within budget)
Recommendation: Ratify Change Order #3B between Mountain View Los Altos High School District and McGuire & Hester to provide services related to the Los Altos High School Student Services Building project.
Approvals:
Recommended By:
Signed By:
Irene Aguilar - Administrative Assistant
Signed By:
Mike Mathiesen - Associate Superintendent
Signed By:
Nellie Meyer - Superintendent
Vote Results: