16.13 Change Order #2B Between Mountain View Los Altos High School District and Duran & Venables to Provide Services Related to the Mountain View High School Auxiliary Gym Project |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
Mountain View Los Altos High School District is requesting Change Order #2B with Duran & Venables be ratified: - Install concrete rings (for raising manhole ring up to grade from underneath.) and raise (5) existing utility boxes to grade and prepare for asphalt work. This is needed to make sure the new asphalt is flush with the boxes. Work to be done on time and materials, not to exceed $16,000. - Existing asphalt at the tennis court is in poor condition (in some locations it has failed). Per District request, demolish approximately 5750 square feet of existing asphalt, dispose and off haul properly, and install new asphalt and prepare for final coating. |
|
|
Funding:
|
$45,072.00 Bond (change order is within budget) |
|
|
Recommendation
|
Ratify Change Order #2B between Mountain View Los Altos High School District and Duran & Venables to provide services related to the Mountain View High School Auxiliary Gym project. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Irene Aguilar - Administrative Assistant |
|
Signed By: |
|
Mike Mathiesen - Associate Superintendent |
|
Signed By: |
|
Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Phil Faillace Moved, Member Fiona Walter seconded to approve the Original motion 'Ratify Change Order #2B between Mountain View Los Altos High School District and Duran & Venables to provide services related to the Mountain View High School Auxiliary Gym project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 4 Nay: 0. | The motion Carried 4 - 0 | | | Phil Faillace | Yes | Sanjay Dave | Yes | Debbie Torok | Yes | Fiona Walter | Yes | |
|
|
|
|
|
|