16.8 Change Order #6D Between Mountain View Los Altos High School District and Atlas Pellizzari Electric to Provide Services Related to the Los Altos High School Student Services Building Project |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
Mountain View Los Altos High School District is requesting Change Order #6D with Atlas Pellizzari Electric be ratified: - provide and install additional electrical items that were not shown on the electrical drawings but are required by Kone Elevator as discussed at the pre-con meeting with Kone’s superintendent on 2/1/23. Additional items needed are as follows: 120V disconnect for seismic shutoff in the elevator machine room, (2) LED lights and (1) GFCI receptacle at the 2nd floor landing, dedicated circuits for lights and GFCI receptacle at the 2nd floor landing. Contractor shall also install (3) conduit runs from the control panel to the elevator shaft for power and low voltage controls wiring. All power & LV wiring will be provided and installed by Kone. - provide and install all conduit and boxes required for the wall mounted digital air flow adjusters that will be provided by the HVAC controls contractor at (31) locations throughout the building. Contractor is requesting to be compensated for this work due to confusion with the scope requirements and design documents during bid time and therefore did not account for this in their bid. |
|
|
Funding:
|
$34,772.00 Bond (change order is within budget) |
|
|
Recommendation
|
Ratify Change Order #6D between Mountain View Los Altos High School District and Atlas Pellizzari Electric to provide services related to the Los Altos High School Student Services Building project. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Irene Aguilar - Administrative Assistant |
|
Signed By: |
|
Mike Mathiesen - Associate Superintendent |
|
Signed By: |
|
Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Catherine Vonnegut Moved, Member Thida Cornes seconded to approve the Original motion 'Ratify Change Order #6D between Mountain View Los Altos High School District and Atlas Pellizzari Electric to provide services related to the Los Altos High School Student Services Building project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Phil Faillace | Yes | Sanjay Dave | Yes | Catherine Vonnegut | Yes | Thida Cornes | Yes | Esmeralda Ortiz | Yes | |
|
|
|
|
|
|