14.19 Resolution No. 23/24-2 Declaring The Futility Of Public Bidding For Eathwork and Paving Trades Bid Package B (Duran & Venebles) For The Mountain View High School Auxiliary Gym Project |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
Since receiving bids and awarding contracts for this project, necessary change orders to the scope of work have exceeded ten percent of the original contract amount. Based on the information as outlined in the resolution, it would be incongruous, futile, and unavailing to attempt to bid the additional work. The change order and accompanying resolution is for work already performed. The resolution is required for contract compliance. The change orders are within the project budget. |
|
|
Funding:
|
|
Recommendation
|
Approve Futility Resolution No. 23/24-2 declaring the futility of public bidding for Eathwork and Paving Trades Bid Package B (Duran & Venebles) for the Mountain View High School Auxiliary Gym project. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
 |
Irene Aguilar - Administrative Assistant |
|
Signed By: |
|
Mike Mathiesen - Associate Superintendent |
|
Signed By: |
|
Nellie Meyer - Superintendent |
|
|
|
|
|
|
|