Subject:
16.9 Change Order #1A Between Mountain View Los Altos High School District and RC Benson & Sons to Provide Services Related to the Los Altos High School Wing 700 Stair Replacement Project  
LCAP (Local Control Accountability Plan) Goal:
 
Enclosure:
 
File Attachment:
LAHS Wing 700 Stairs_RC Benson CO #1A_01.24.22.pdf
 
Summary:
Mountain View Los Altos High School District is requesting approval of Change Order #1A with RC Benson & Sons:
- Cost to re-mobilize equipment and crane due to new stairs not being procured after existing stairs were demolished
- Remove existing tube beam at North stairs due to changes from bid set to DSA set
- Revise design for middle guard handrail detail
- Add paint stripe at landing per IOR request as stipulated by CBC requirements
- Provide and install bent Z plate at top of stairs
 
Funding:
$19,572.00
Bond
 
Recommendation
Ratify Change Order #1A between Mountain View Los Altos High School District and RC Benson & Sons to provide services related to the Los Altos High School Wing 700 Stair Replacement project.  
Approvals:
Recommended By:
Signed By:
Irene Aguilar - Administrative Assistant
Signed By:  
Mike Mathiesen - Associate Superintendent
Signed By:  
Nellie Meyer - Superintendent
 
Vote Results:

Original Motion
Member Fiona Walter Moved, Member Debbie Torok seconded to approve the Original motion 'Ratify Change Order #1A between Mountain View Los Altos High School District and RC Benson & Sons to provide services related to the Los Altos High School Wing 700 Stair Replacement project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Phil Faillace     Yes
Sanjay Dave     Yes
Debbie Torok     Yes
Catherine Vonnegut     Yes
Fiona Walter     Yes